NonLabour Units
In the Open Standard
Andrew TanMember for 22 years 1 month
- Created
- 0
- 13
0
Hi,
I was trying to generate a non-labour units curve.
HOwever,
The actual non-labour units is 0, the activity is 100% complete.
The remaining nonlabour units is 0, the budgeted nonlabour units is 1020.
Can I generate a earned non-labour untis or do some settings to associate the actual with physical % complete.
Thanks,
Andrew