Skip to content

NonLabour Units

Andrew TanMember for 22 years
Created
0
2
0

Hi,

I was trying to generate a non-labour units curve.

HOwever,

The actual non-labour units is 0, the activity is 100% complete.

The remaining nonlabour units is 0, the budgeted nonlabour units is 1020.

 

Can I generate a earned non-labour untis or do some settings to associate the actual with physical % complete.

Thanks,

Andrew

Replies

Oldest first

No replies yet. Be the first to answer.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?