NonLabour Units
In the Open Standard
Andrew TanMember for 22 years
- Created
- 0
- 2
0
Hi,
I was trying to generate a non-labour units curve.
HOwever,
The actual non-labour units is 0, the activity is 100% complete.
The remaining nonlabour units is 0, the budgeted nonlabour units is 1020.
Can I generate a earned non-labour untis or do some settings to associate the actual with physical % complete.
Thanks,
Andrew
Replies
Oldest firstNo replies yet. Be the first to answer.
Log in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?