Login Dialog : "The database has not been configured to run background jobs..."

Shane PouchMember for 18 years 8 months
Created
1
2
0

Hello to all,

I am trying to find out why a certain dialog box appears right after I login to P6.  

So, the P6 "Login to Primavera P6" dialog box comes up on starting the program.  I plug in my password, and the the login dialog box title changes to "Connecting to database...", then "Validating user...", then this is when I get a "Primavera P6" dialog box with the following text and an "OK" button:
 
Can someone 1) explain what this means, and 2) how it can be resolved?  

Thanks in advance for your help!

1 reply

Oldest first
  1. 0
    Rafael Davila ·

    Try logging into SQL Server

    Try logging into SQL Server 2005 Express and highlight the pmdb$primavera database. Click on New Query and paste the following command on the query pane at top right:

    select log_time, source, type, description from dbo.bgplog;

    then click on Execute and that is all.

    If it works good, but don't ask me why, is a solution I read somewhere else.