EV Calulations

Dewald du PlessisMember for 15 years 7 months
Created
3
1
0

Just would like to find out can you set the earned value calculations to use resource units? ev=units vs time. if yes where do i change this, or can you only base the earned value as ev= cost vs time.

3 replies

Oldest first
  1. 0
    Arend Kok ·

    Hi Dewald.   What I normally

    Hi Dewald.

     

    What I normally do in situations like these, is to set my resource rates to 1$ and to remove all expenses.

     

    The progress percentages you see then are purely based on units.  There is also a earned units column if that helps.

     

    Regards,

     

    Arend Kok.

  2. 0
    Amit Parmar (PMP) ·

    Hi Dewald, You can also do

    Hi Dewald,

     You can also do the following to calculate EV at resource level :

    1) Add two resource assignment level numeric user defined fields. For example "UNITS % COMPLETE Calc" and "Resource EV"

    2) Add a Global change with the following 'Then" statements and run the change:

    a) "UNITS % COMPLETE Calc" equals Units % Complete \ 100. Primavera populates Units % Complete as a whole number and we need the  number stored as a decimal.

    b) "Resource EV" equals "UNITS % COMPLETE Calc" x Budgeted Cost or Budgeted Units.

    Note - Solution courtesy Primavera Support.

    Regads

    Amit Parmar

    Check out my blog on Primavera at http://www.primaverablog.in

  3. 0
    Dewald du Plessis ·

    just to finalise do i need to

    just to finalise do i need to set my activity %complete type to Physical? or can i leave it as duration

Log in or join to reply