Finish to Start Relationship -Lag =0; Predecessor finish date and successor start date is same

Prabu DevaMember for 19 years 8 months
Created
3
1
0

I have prepared a schedule in P6 with activities having finish to start relationships after scheduling the the finish date of the predecessor activity and the start date of the successor activity remains same while the start date of the successor activity should be one day after the finish date of the predecessor,what may be the likely problem in P6 settings please advice

3 replies

Oldest first
  1. 0
    Alexandre Faulx-Briole ·

    Prabu,display the time along

    Prabu,

    display the time along the date (Edit, User Preference, Dates); you should see that the tasks do not finish by the end of the day, but some time earlier, for instance 3:00 PM instead of 5:00PM

    then the successor task will start from 3:00 PM instead of 8:00 AM the following day

    the reason is that you have discrepancies in the calendars: open the project and/or the tasks calendars, display the Standard Week and you will certainly notice that the working hours do not finish with the end of the day, but earlier.

    Amend every such calendars, re-schedule the project, it should be ok then

    good luck,

    Alexandre

  2. 0
    Henry Hermosura ·

    Hi Alexandre, what if you are

    Hi Alexandre, what if you are using more that one calendar work days how to fix this 

    Predecessor finish date and successor start date is same? Any idea?

  3. 0
    Zoltan Palffy ·

    there are 10 items to

    there are 10 items to check 

    item #1 as stated by Alexandre check your TIMES turn them on by selecting Edit, User Preference, then select the Dates tab at the bottom under Time select 12 hour and show minutes

    item #2 Also check you durations in the users preferences click on the Time units and under Durations Format make sure that the decimal is 2 places. If you have ANY original durations or remaining durations that that are not whole numbers change these to whole numbers.

    item #3 check ALL constraint dates for the start constraints make sure that the start TIME is 8:00 am or the earliest time in anyy of your calendars being used.

    item #4 check ALL constraint dates for the finish constraints make sure that the finish TIME is 5:00 pm or the end of the latest time in anyy of your calendars being used.

    item #6 make sure that your Project START TIME is 8:00 am or the earliest time in anyy of your calendars being used.

    item #7 make sure that your project must finish by date TIME is correct the finish TIME should be 5:00 pm or the end of the latest time in anyy of your calendars being used.

    item #8 for any activites that are in progress make sure that the actual start date TIMES are correct that the ACTUAL START TIME is 8:00 am or the earliest time in anyy of your calendars being used.

    item #9 make sure that the data date TIME is correct make sure that the start TIME is 8:00 am or the earliest time in anyy of your calendars being used.

    item #10 if all of these are correct then select tools then schedule then options then at the bottom where it says calendar fir scheduling Relationship Lag select Successor Activity calendar.
     
    theses are the only things that can affect this.

Log in or join to reply