SDK
In the Open Standard
Susan YoungMember for 23 years 7 months
- Created
- 2
- 2
0
Hello everybody,
Probably a this has been addressed in other threads too but I am a newbie & would really appreciate a detailed answer if possible.
How do u import a WBS from Excel to P6 ?
I know of the excel file ''PATTLNK_..........xls' Tried using it, but get an error message. So i guess ODBC is not set right. How do I do it ?
I have also heard of the 'parser' file but dont know how to use it. Would appriciate details if it works for importing WBS into P6.
Thanks in advance
Sue
2 replies