Poblem with Performance % Complete & Schedule % Complete
In the Open Standard
Irfan KhanMember for 17 years 3 months
- Created
- 0
- 2
0
hi to all experts,
I have problem with Performance % Complete & Schedule % Complete. as per the first picture my Performance % Complete was showing 17.92% on the data date 11-April-2011. on the 14th April 2011 i run my store period performance after this my Performance % Complete & Schedule % Complete is showing 0%.
pls tell me any solution bcz i am in trouble.
thanks...
Replies
Oldest firstNo replies yet. Be the first to answer.
Log in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?