P6 Calendar - modify work hours
In the Open Standard
Ife OlykeMember for 19 years 8 months
- Created
- 0
- 1
0
Hi Planners,
I have an activity (let’s say its activity ‘A’) within my P6 plan that will take 6 hours to complete and has a fixed start date and time. In carrying out this task, no other activity can be progressed. I need to make this visible in the P6 plan by setting the work hours for activity ‘A’ on the day as ‘Nonwork ‘. Alternatively, I could set the whole day, but that will portray a false impact on the schedule duration.
Who has got an idea? Thanks
olyke
Replies
Oldest firstNo replies yet. Be the first to answer.
Log in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?