P6 Calendar - modify work hours

Ife OlykeMember for 19 years 8 months
Created
2
2
0

Hi Planners,

I have an activity (let’s say its activity ‘A’) within my P6 plan that will take 6 hours to complete and has a fixed start date and time. In carrying out this task, no other activity can be progressed. I need to make this visible in the P6 plan by setting the work hours for activity ‘A’ on the day as ‘Nonwork ‘. Alternatively, I could set the whole day, but that will portray a false impact on the schedule duration.

Who has got an idea? Thanks

 

olyke

2 replies

Oldest first
  1. 0
    Gary Whitehead ·

    Could you not just make

    Could you not just make Activity A a predecessor of all other activities?

    If you try and do it with calendars, what happens if Activity A is delayed?

  2. 0
    Ife Olyke ·

    Please ignore post, problem

    Please ignore post, problem solved.