viewing relationships with baseline bars displayed

Gary WhiteheadMember for 17 years 7 months
Created
3
14
0

When you are displaying both current project and a baseline bar and select "show relationships" from barchart options, the relationship lines are shown linking the baseline bars and not the current project bars.

 

Anyone know of a way to fix this?

 

Cheers,

 

G

3 replies

Oldest first
  1. 0
    Ferdinand U. ·

    from barsmove the display

    from bars

    move the display name of remaining bar on top of the baseline bar

  2. 0
    Gary Whitehead ·

    Thanks, Ferdinand.   -I had

    Thanks, Ferdinand.

     

    -I had just worked it out myself, but your swift reply means none of my colleague's believe me!

     

    Cheers,

    G

  3. 0
    Ferdinand U. ·

    hi garythis trick is not my

    hi gary

    this trick is not my idea

    i just learned it from one of paul harris' technical papers online last year

    http://primavera.com.au/Technical%20Papers/100602_P6V_%20Bars_Tricks_and_Traps.pdf