Skip to content

How to show the actual % complete on the baseline bar

Kumar SMember for 16 years 8 months
Created
0
3
0

Dear Experts,

Is there any work around to show in the ghantt chart bars  the actual bar completion inside the baseline bar.

for example in the when i view the baseline bar if the perticular activity is scheduled to finish 50% complete then in the baseline bar half of the bar should be one color and the other half another color.

can this be done in p6.

Thanks in advance

 

Replies

Oldest first

No replies yet. Be the first to answer.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?