Showing Early and Late Cost curves in P6

Sebastian DiBlasiMember for 15 years 6 months
Created
2
4
0

I have a baseline cost loaded schedule that I want to see cost curve based upon the early and late dates. The profile can generate early, but not late. Is there a way to do this? Also is there a way to show in tabular form the cost by early and late dates?

2 replies

Oldest first
  1. 0
    Karim Ragab ·

    Me too

    Me too

  2. 0
    Khaja Sharief ·

    Select activity

    Select activity usage/resource usage profile. Now right click on the graph and select activity usage profile options/ resource usage profile options.  Under bars/curves area, select the remaining early or remaining late. You can play around this, you can veiw this in terms of units as well as costs. 