Creating UDF and Distributing Similar to Activity Usage Spreadsheet

Jon-Michael GravesMember for 15 years 4 months
Created
1
1
0

Hi Everyone:

I am trying to figure out a way to distribute a user-defined field (qty) across activities like what is done on the activity usage spreadsheet. I want to avoid entering nonlabor units, etc. as the schedule is updated solely on earned hours. Any suggestions? I am willing to use Excel as an alternative to doing this in P6.

 

Jon

1 reply

Oldest first
  1. 0
    Paul Harris ·

    My understanding is that it

    My understanding is that it can not be done. I usually use Exenses to get a cash flow without using resources.

    There is an article on my website www.primavera.com under technical articles that shows how this can be achieved using Excel and there are some samples to work with.

    Paul E Harris

    Eastwood Harris Pty Ltd, Melbourne, Australia

    Planning and Scheduling Training Manual & Book Publishers, Consulting and Training

    www.eh.com.au

    www.eastwoodharris.com

    www.primavera.com.au- a Primavera scheduling software resources site