Importing Schedule
- Created
- 3
- 1
Guys I need some help...I am working in P6 in my office and exported my schedule in xer format so I can work at home. After importing the file in my laptop, I noticed that the durations have been changed as well as the start/finish dates(calendar settings did not change, 10working hours/day,7am to 6pm w/ 1 hr break), the start dates are at 8:00AM and finish dates at 5:00PM (8hours only,1hr break) although the calendar settings is at 10hrs/day..i tried to reschedule but still it, finish dates are still ending at 5:00PM and still calculating at 8hrs/day work.in the first place, duration shall not change after I imported the file and all the settings shall have been preserved...Any solution???
Thanks,
Ariel