Planning Unit in P6

Adekunle ArisilejoyeMember for 18 years 6 months
Created
1
3
0
Hello, please what determins what planning unit to use when you are creating a schedule (hr, day or month). Cheers kay

1 reply

Oldest first
  1. 0
    Manoj VS ·

    Hai Bobo Kay,My suggestion is

    Hai Bobo Kay,

    My suggestion is Planning unit depends on requirement of the project / activities of the project. Project like shutdowns which require monitoring hourly basis planning unit is hr,  and for projects for which hourly basis monitoring not required day can be planning unit.

    Regards