Baseline dates

Manoj VSMember for 17 years 3 months
Created
3
2
0

Hi

In p6 when a baseline is created from a schedule- start, finish date differ from BL start and BL finish for some activities in that schedule. Is there any reason for this. Please advise me.

 

Thanks in advance.

3 replies

Oldest first
  1. 0
    Mukunda Y ·

    Manoj..Basleline is always

    Manoj..

    Basleline is always Baseline, start & finish dates will change after updating the schedule. It is because of actual dates insertion & rescheduling.

     

    Regards

    Mukunda

  2. 0
    Manoj VS ·

    Dear Mukunda,My problem is in

    Dear Mukunda,

    My problem is in primavera BL start and BL finish shown is different for some activities without updating

  3. 0
    A D ·

    It might be because there are

    It might be because there are actual dates in the baseline schedule. Change the earned value setting under Admin Preferences. (Instead of planned dates you can change it to Current dates).