Cannot delete relationship that has been created initially.

Krishna KumarMember for 19 years 8 months
Created
1
1
0

Hi Planners,

In P6, I can't able to delete the relationship that I've linked before. Even after deleting it, it is reappearing again. How do I delete it permanently? Is there any option in P6?

Kindly help me to resolve this problem.

 

Regards,

Krishna

1 reply

Oldest first
  1. 0
    Alexandre Faulx-Briole ·

    Krishan,there is no specific

    Krishan,

    there is no specific option or setting to permanently or "not-permanently" un-link activities in P6 or whatever; you should be able to delete the relationship between two specific activities either by double-clicking the relationship line and display the small dialog box where you will click "Delete"; or display the Relationships / Links tab in the Task Detail form, select the task you want to unlink, select the Predecessor or Successor side, select the link you want to supress, click Supress

    however, it happened once when I was giving a trainin session that one trainee was not able to unlink tasks at all; the only way-round I had found was to delete the tasks and create them anew; I guess there is a bug somewhere in the software, that creates this behaviour

    Hope it helps

    Alexandre