Resources Curves

Natalia BarrosoMember for 19 years 9 months
Created
0
1
0

Dear,

 

I am using resources curves in P6, the issue is that after several months I changed one resource curve and the following message pop up in the screen "the new curve definition will not recalculate actual units & costs until the resource assigment is updated". After this message I have tried several thing to solve this problem but the curve does not work, it means that the budget quantities are not distributed along the time. Anybody knows what should I do "update the resource assigment"?.

 

Thanks in advance

 

Natalia Barroso. PMP