Global Change for Calendars

Jeremey SmithMember for 15 years 4 months
Created
2
4
0

What criteria need to set up in Global Change to change the Calendar from 7 weeks to 5 weeks which may change calendar of all actvities?

Thanks

2 replies

Oldest first
  1. 0
    Shah. HB ·

    Hi Jeremy Smith1. Create a

    Hi Jeremy Smith

    1. Create a calendar of 5 Weeks 

    2.Filter the activities you need change (If any )

    3.Use file down option to replace 7 weeks to 5 weeks

    ///Is it weeks or days?///

    Regards

    Shahul

  2. 0
    Ranjit Kumar Kumar ·

    Hi Jeremy Simth, Select

    Hi Jeremy Simth,

    Select Enterprise > Calendar > Add > Select any Calendar from the existing calendar > Modify > Work week > Which day you want to off put 0 or other wise put all 8 hours then it will change from 5 work days to 7 work days > Click on the Default.

     

    Assigning the 7 days work week to all the activities.

    View > Columns > Click on the General and find out the Calendar > Ok

     

    Change the existing calendar by the new calendar in one cell.

    After wards click on the new cell (new calendar cell) then use the command shift and select all the activities > go to the Edit > fill cell.

    I hope it will work

    Thanks and regards,

    Ranjit