Global Change Summary Task Actual % Complete

Mukunda YMember for 17 years 11 months
Created
4
2
0

Dear Experts...

Summary task % Complete =((Sum of Completed duration of the Baseline Activities Duration)/(Sum of Baseline Activities Duration))*100.

I want to Calcualte the Sumaary task % Complete Based on the Baseline Duration, not based on the Actual Remaining duration. I know to do this in Microsoft Project,...How to do it in primavera using Global Change,,,

I hope my querie is clear...

 

Regards

Mukunda

4 replies

Oldest first
  1. 0
    Mukunda Y ·

    I have inserted user_text 1

    I have inserted user_text 1 Column able to write the text in the activities row, not able to write the text, in the WBS row,,,how to do this,,,

     

    Regards

    Mukunda

  2. 0
    Mukunda Y ·

    Dear Experts...i am

    Dear Experts...i am astonishing no reply from day,,, is there no way to do these?

  3. 0
    Richu Rose ·

    Hi Mukunda, Try using

    Hi Mukunda,

    Try using UDF.

    Regards,

    Richu

  4. 0
    Mukunda Y ·

    Dear Richard,,,, \Thank u for

    Dear Richard,,,, \

    Thank u for reply,,, in UDF we can enter only the text or number or interger, we cannot enter the formula in UDF, ,,, can enter the formula only in Global Change,,dont know much about Global change,,,, hope u understand my problem,,,,

    Regards

    Mukunda

Log in or join to reply