Cost loading updates problems

Ahmed MoheyMember for 15 years 3 months
Created
5
2
0

Regarding loading the schedule with cost what happens when updating that the actual cost is keeping changed for the nearly ended monthes i think becouse if there is an activity where its duration is is extended beyound its original duration so the program is re-distributing the money again on the new forcasted duration my question is is there any possible way where can i fix the money for the passed duration and only re- distribute on the remening duration only without changing the actual???

5 replies

Oldest first
  1. 0
    Ferdinand U. ·

    store period performance for

    store period performance for specified financial periods

  2. 0
    Ahmed Mohey ·

    i have tried it but it didnt

    i have tried it but it didnt work may be i am doing it with the wrong procedure so please if u can tell me the right steps to do it i will be great thanks so much

  3. 0
    Rafael Davila ·

    Beware that even with

    Beware that even with pre-defined financial periods your reports can still be wrong.

    It is not unusual for payments to lag accrual periods so some data entry must be done after the period. This shall not be an obstacle to get scheduling reports that do not include financial data and then latter on reports that include financial data as accrued. Cash basis and accrual basis are not the same but job costing is performed on accrual basis no matter when the payment were performed. Cash flow on the contrary is based on the date the checks are issued.

    Photobucket

  4. 0
    Mark Greenhalgh ·

    It is best to keep actual

    It is best to keep actual costs in separate activities where you can absolutely control the actual dates.  Don't keep them in an activity that could have a date changed for any reason.  Have you tried Longest Path Approximator?  http://scheduling.spacetechnology.net  It is capable of moving the data date back to the beginning of the month, and then you can see the critical path.  Hint:  Ask for  a free sample!

  5. 0
    Amit Parmar (PMP) ·

    Hi Ahmed,Ferdinand is right,

    Hi Ahmed,

    Ferdinand is right, you need to use Financial Periods. Check the following link http://primaverablog.in/category/important-topics/financial-periods/

    If you have any questions, pls feel free to ask.

    Regards

    Amit

    Check out my blog on Primavera at http://www.primaverablog.in

Log in or join to reply