Grouping band

Raed HusseinMember for 19 years 4 months
Created
2
1
0

if the activities used more than calendar how p6 calculate the variance finish or start for grouping band

2 replies

Oldest first
  1. 0
    Mike Testro ·

    Hi Raed As far as I am aware

    Hi Raed

    As far as I am aware only one calendar can be assigned to a task.

    Different calendars can be assigned to resources allocated to the task - in which case chaos reigns.

    Best regards

    Mike Testro

  2. 0
    Gary Whitehead ·

    Durations and, I assume

    Durations and, I assume variances also, of grouping bands are calculated using :

    • The Database Default Calendar and
    • The hours/day setting under Edit>User Preferences>Time Units

     

    The below links to a presentation by Paul Harris which covers this and other common issues:

    http://www.eh.com.au/Technical%20Papers/100602_P6V_%20Bars_Tricks_and_Traps.pdf