Cost Loading the Schedule
In the Open Standard
Dost HydMember for 15 years 2 months
- Created
- 9
- 3
0
Hi,
I would like to cost load the schedule. I do not want to cost load it based on units/time. I want to give an activity a Lump Sum Budgeted Cost. Get a cost curve to see how much we would be spending per month.
I have created a Non-labor Resource called Budget and physically typed in the Budgeted cost. That is the only way I knew. But, I guess that is not very effective.
Can any one tell me the best way to cost load a schedule and obtain a cash curve?
Thanks Much.
Dost.
9 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?