Please i need help with a proficient P6 Planner user !!!!!!!!!!!!!!!! HELPPPPPPPPPPPPPPPPPPPP HeLPPPPPP
- Created
- 4
- 5
Just want to validate this with youuuuu. I am confined to primavera p6 so there's no alternative. please advice if you have recently used primvera p6 or very conversant with p6
1. You plan in p6 lets say PLanA
2. Now you update by selecting project, maintain baseline, then copy. this will save a copy of your original plan.......
3. You select project Assign baselines and make this your project baseline and primary baselines.....
4. Then you update your plan with the actuals and so onnnn.
Now you want to replan so you UNLINK your baseline from your PlanA then you replan..... PLan A <R>
My question is if you want to unpdate the second time or after you have amended your plan wat will make ur baseline.........
please HeLPPPPPPPPPPPPPPPPPPPPPPPPp
4 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?