Total Float - Is it possible to change the driver to within a WBS Code?

Chad JonesMember for 15 years 2 months
Created
4
0
I have a schedule, with 1700 WBS Codes.
Within each WBS Code I have 5-20 activities.
I would like the total float to be driven from a certain activity within each WBS Code.
So basically every WBS acts as it's own entity.
Right now, all Total Float is driven from the Latest Finish Date of the entire schedule.

Is this possible?
If yes, please give me a hint :)

4 replies

Oldest first
  1. 0
    Chad Jones ·

    Well, I've found out there is

    Well, I've found out there is no way to globally change the driver for Total Float to per WBS.

     

    What I need to do is set my last activity in each WBS to Mandatory Finish.

     

  2. 0
    Ram Kumar ·

    Dear Jones, I think that's

    Dear Jones,

     

    I think that's the only way........................

  3. 0
    Paul Harris ·

    In the Tools, Schedule,

    In the Tools, Schedule, Options, select "Make open ended activities critical" and all activities without successors will calculate their own critical path.

    Paul E Harris

    Eastwood Harris Pty Ltd, Melbourne, Australia

    Planning and Scheduling Training Manual & Book Publishers, Consulting and Training

    www.eh.com.au

    www.eastwoodharris.com

    www.primavera.com.au- a Primavera scheduling software resources site

  4. 0
    Chad Jones ·

    Rock on Paul Harris!!!! Thank

    Rock on Paul Harris!!!! Thank you very much!!