Assigned Resources
In the Open Standard
Ung Yu LauMember for 18 years 9 months
- Created
- 0
- 1
0
Any idea, I was assigned resources into my baseline programme in term of budgeted unit and cost but remaining quantity didnt changed figure as budgeted unit. e.g.
Budgeted unit 10m2 and remaining quantity should be maintain 10m2 because i didnt do any update yet.
Replies
Oldest firstNo replies yet. Be the first to answer.
Log in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?