Show Remaining Units by Shift for all Resources

Josh RobertsMember for 15 years 2 months
Created
3
3
0

I am having trouble getting the Planned or Remaining Units by Shift into an Excel file. I think I figured out a way using the Resource Usage Spreadsheet but I can't get all the resources to show up all at once. Is there a way to allow you to view planned units by shift with every active project resource. I can just copy each resource one at a time but I would rather do them all at once. P3 was very easy to extract this data and I am having a little trouble doing the same thing in P6.7. This information would be used for an S-curve in Excel. Any help Would be greatly appriciated.

 

Thanks,

Josh

3 replies

Oldest first
  1. 0
    Kumar S ·

    Dear Josh,   You can get the

    Dear Josh,

     

    You can get the loading of  Planned or Remaining Units shift wise by report.

    I have a report format where you will get the loading shft wise.

    send me your mail id i will forward it.

     

    Cheers

  2. 0
    Mike Testro ·

    Hi Kumar You can use the PP

    Hi Kumar

    You can use the PP private message service.

    Best regards

    Mike Testro

  3. 0
    Josh Roberts ·

    I think I might have figured

    I think I might have figured it out. I ran a Resource report using Resource name and adjusted the timescale accordingly.  If you don't mind, could you send me your format anyway so I can see if it might be diffrent? JRoberts@dow.com

     

    Thanks in advance,

    Josh