P6 V7 Remining Units
- Created
- 1
- 2
Just upgraded to P6V7
Something seems wring in the remaining Units field does any body have anyideas ?
Budgeted Labour Units 538Hrs
Physical % Complete is 38 %
Unit % Complete is 38 %
Actual Units = 269 (Automatic update)
At Completion Labour Units is 707.9 Hrs (Automatic update)
Remaining Labour Units is 438.9
Setting
Admin Preferences
ETC=Remaining cost for Activity
Activity Settings
Task Dependent
Fixed Duration and Units
Physical
Project Settings
Link Budget and At Completion for not Started activities
Reset Remaining Duration and Units to Original
Subtract Actual from at Completions
When I change At Completion labour Units to 538 it recalculate Units % Complete to 50 % and Change Remaining Labour Units to 269
The answer I want is the following
Budget = 538 Hrs
% Complete is 38 %
Earned value is 204
Remaining Hours is 333
How do I get P6V7 to do this ?
1 reply
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?