P6 V7 Remining Units

Jay StadlerMember for 15 years 2 months
Created
1
2
0

Just upgraded to P6V7

Something seems wring in the remaining Units field does any body have anyideas ?

 

Budgeted Labour Units 538Hrs

Physical % Complete is 38 %

Unit % Complete is 38 %

Actual Units = 269 (Automatic update)

At Completion Labour Units is 707.9 Hrs (Automatic update)

Remaining Labour Units is 438.9

 

Setting

 

Admin Preferences

ETC=Remaining cost for Activity

 

Activity Settings

 

Task Dependent

Fixed Duration and Units

Physical

 

Project Settings

Link Budget and At Completion for not Started activities

Reset Remaining Duration and Units to Original

Subtract Actual from at Completions

 

When I change At Completion labour Units to 538 it recalculate Units % Complete to 50 % and Change Remaining Labour Units to 269

 

The answer I want is the following

Budget = 538 Hrs

% Complete is 38 %

Earned value is 204

Remaining Hours is 333

 

How do I get P6V7 to do this ?

1 reply

Oldest first
  1. 0
    kevin kianpour ·

    I believe, when Physical PCT

    I believe, when Physical PCT is used, both % and remaining durations must me updated. Based on remining duration and units per day, Remining Hours are calculated. Also the earned value calculation method should ve visited, under, wbs screen, earned value tab. Make sure the Performance measure type is set to activity pct.