Resource Working Alternate Months How to Model this in Primavera

Muhammad Zeeshan KhanMember for 18 years 7 months
Created
1
3
0

Oh HI Guys

I hope you are doing well.

One my resource is working alternatively on my project how do i model this resource hours on my plan

Package A 

Resource X

working 2 days  Jan , Mar , May, July , Sept , Nov.

I have used suspend activitu but it does not work

Any other suggestions will be appreciated  

 

1 reply

Oldest first
  1. 0
    Kumar S ·

    Dear, I think the easiest way

    Dear,

    I think the easiest way is to create a calendar based on your working criteria that is alternate months and 2 days working.

     

    Cheers,