Resource Working Alternate Months How to Model this in Primavera
In the Open Standard
Muhammad Zeeshan KhanMember for 18 years 7 months
- Created
- 0
- 1
0
Oh Hi I hope you are doing good
Can you please help me modelling Resource hour in my schedule who works alternate months
So lets assume
if Resource X is working on Package A and he works 2 days in Jan March May July Sept Nov
How do i model this in primavera so it reflect in my activity usage spread sheet like this
Jan Feb Mar Apr May Jun July Aug Sep Oct Nov
2 2 2 2 2 2
Thanks in Advance
Replies
Oldest firstNo replies yet. Be the first to answer.
Log in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?