Restore Base line
In the Open Standard
Arun VasanthMember for 17 years
- Created
- 2
- 2
0
Dear friends
Please guide me how to restore the base line program from the updated program.
I made a big mistake .I prepared the base program and updated with base prgram
as current project .I did nt mmake a single copy or back up of the base program & the progress updation is almost 40 % completed.
Regards
Arun .V
2 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?