Skip to content

Restore Base line

Arun VasanthMember for 17 years
Created
2
2
0
Dear friends Please guide me how to restore the base line program from the updated program. I made a big mistake .I prepared the base program and updated with base prgram as current project .I did nt mmake a single copy or back up of the base program & the progress updation is almost 40 % completed. Regards Arun .V

2 replies

Oldest first
  1. 0
    Jash Sales ·

    Arun, Go to Project ~ assign

    Arun,

    Go to Project ~ assign baseline: used <current project> as your project baseline/ user primary baseline, then go to maintain baseline~ click restore.

    gudluck!

    Jash

  2. 0
    Arun Vasanth ·

    Thank you Jashhhh

     

    Thank you Jashhhh

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?