Schedule % complete

Olivia RSAMember for 15 years 1 month
Created
4
1
0

Hi,

I need to do a program for work and I need to display schedule complete. It currently shows 0%, how do i change it to show relative to the start and completion dates i put in the program

Im using p6v7

Thank you in advance :)

4 replies

Oldest first
  1. 0
    Olivia RSA ·

    figured it out ;)

    figured it out ;)

  2. 0
    Olivia RSA ·

    figured it out ;)

    figured it out ;)

  3. 0
    Raymund de Laza ·

    Ryan,Just load any resource

    Ryan,

    Just load any resource to all activity with budget unit=1 and price per unit=1.

     

    Hope it helps.

     

    Regards,

  4. 0
    Mukunda Y ·

    ryan, assign budget unit=1

    ryan, 

    assign budget unit=1 and price per unit=1.

    assign & maintain baseline,

    start to update with actual dates.

Log in or join to reply