P6 Rel 7 Lag

Ahmed KHRMember for 15 years 11 months
Created
4
2
0

Dear planners;

When I run the update on P6 rel 7 , some activities don't start directly after the precedor one (See pic below)!

The lag on the relationship=0, and no Constraint.

Why I get this kind of probleme?

 

Regards,

4 replies

Oldest first
  1. 0
    Gary Whitehead ·

    I can't see your picture, but

    I can't see your picture, but this could be caused by:

    -activty calendars

    -other predecessors

    -resource levelling

    -resource calendars

    -project calendars

    -calendar shift patterns

  2. 0
    Thaer Ghanim ·

    hi Go to (Tool) from (Menu

    hi

     

    Go to (Tool) from (Menu Bar),choose (Schedule ),Choose (Option),in General Tab ...down of the widow you can find

    (Calender for schdeuling lag relation) --check what calender you are using in this option .

     

  3. 0
    Ahmed KHR ·

    Sorry don't work

    Sorry don't work

  4. 0
    Ahmed KHR ·

    Don't work.

    Don't work.