Skip to content

FLoat Bars in Primavera P6

Brave GMember for 15 years 11 months
Created
6
3
0

Completed activities are showing float bars tilll the project finish date. Is that right in p6.

 

 

Does anyone know this..

 

Thanks

6 replies

Oldest first
  1. 0
    Simon Willson ·

    Hi Geoff, If your tasks are

    Hi Geoff,

    If your tasks are open ended then they will have float until the end of the project.

    Regards

    Simon

  2. 0
    Rafael Davila ·

    In addition to open ended

    In addition to open ended activities...

    From http://ronwinterconsulting.com/Understanding_P6_Dates.pdf 

    Many P6 users are puzzled to see complete activities where early and late dates differ from actual dates. Does that mean P6 calculates early and late dates for complete activities? If so, total float for complete activities can be calculated.

  3. 0
    Amit Parmar (PMP) ·

    Hi Geoff,This happens if you

    Hi Geoff,

    This happens if you are using "Retained Logic" as your scheduling option. Primavera needs to calculate Early and Late dates in case it has to calculate the dates for the Not Started Successor activities. If you use "Progress Override" or "Actual Dates" in scheduling options, Primavera will stop calculating Early and Late Dates for Completed activities. For more clarity on Scheduling Options, check this link at http://primaverablog.in/2011/07/scheduling-options-%e2%80%93-progressing-activities/

    Simon- Even  open ended but Finished activities will not have float if you use Progress Override or Actual Dates in scheduling options

    Regards

    Amit

    Check out my blog on Primavera at http://www.primaverablog.in

  4. 0
    Brave G ·

    Guys,   Some of this

    Guys, 

     

     

    Some of this activities have logic and have been completed and are still showing float bars extending to the project finish date.

     

     

  5. 0
    Utku Çil ·

    Geoff,1. Right click on Gannt

    Geoff,

    1. Right click on Gannt Chart

    2. Select Bars

    3. Change the filtering option for "Float Bar" from "All Activites" to "Not Started" & "In Progress"

     

    I hope this helps.

    Regards,

    Utku.

  6. 0
    Brave G ·

    You are starrrr. Thanks for

    You are starrrr. Thanks for reminding....

     

    That is so rightttttttttttttttt....

     

     

    Geofff

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?