calenders & resources
In the Open Standard
Gary ListerMember for 25 years 5 months
- Created
- 11
- 7
0
Please if anybody can help
i am running a master schedule with multiple calenders
most of the activities are 6 days but the elapsed duration is 17 days, calendar i am having a problem with is daily calendar 6 hours a day working everyday, one task 54 hours which is 9 days duration is taking over 31 days to complete - why
11 replies