How to assign the same baseline to monthly updates?
In the Open Standard
J SMember for 15 years
- Created
- 9
- 4
0
How can I assign the same baseline schedule to my current schedule every month? Right now I make a copy of the baseline schedule and assign it as a baseline to my current schedule which means I have a copy of one baseline for each month. I want to avoid making copies. Is there a way to work around this?