How to assign the same baseline to monthly updates?
In the Open Standard
J SMember for 15 years
- Created
- 2
- 2
0
How can I assign the same baseline schedule to my current schedule every month? Right now I make a copy of the baseline schedule and assign it as a baseline to my current schedule which means I have a copy of one baseline for each month. I want to avoid making copies. Is there a way to work around this?
2 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?