Can somebody point the way to some practical examples of linking P6 to revit software? Thanks

2 replies

Oldest first
  1. 0
    Baris Hazar ·

    Is it AutoDesk's Revit? If

    Is it AutoDesk's Revit? If so, I didn't know that Revit has such a feature. I have some info of Navisworks for 4D planning.

  2. 0
    D Artagnan ·

    You cannot link the Revit

    You cannot link the Revit directly to P6/P3 or to any scheduling software. You need a third-party software like Navisworks, Synchro, etc.