User-Defined Filed and Global Change
In the Open Standard
Muhammad AsimMember for 15 years
- Created
- 8
- 4
0
Hi:
I have createrd a User-Defined field "Working Days". Now through a Global Change I want to assigne "Orignal Duration" to User-Defined Field "Working Days". For example Orignal Duration = 10d, then after Global Change Working Days becomes Working Days= 10.
Anybody can help me.