Look Ahead Schedule Presentation
- Created
- 13
- 4
Dear Planners,
I have encountered a problem in filtering the Look Ahead schedules wherein some of the activities that is ongoing does not appear on the look ahead schedule. in principle this must be shown. Tried to look into the samples of the look ahead schedule in P6 but seems it is not working.
Any help please.
Thanks
13 replies
Oldest first- 0SHShah. HB ·
Hi Henry ChiuHave a look at
Hi Henry Chiu
Have a look at filter condition you defined for look ahead layout.May i know the condition you defined ?
Cheer's
Shahul
- 0HCHenry Chiu ·
Hi Shahul, Following
Hi Shahul,
Following filter is my condition
Where Early Start is within range DD DD+3W
Physical % Complete is not equal to 100%
Remaining Early Start within range DD+0D DD+3W
With All of the Following is the condition
After imposing this filter some activities with progress and is ongoing is not shown. Our client planner noticed my presentation as incomplete. After our planning meeting, I then study how to show the ongoing activities but failed.
If I will add another condition Activity Status in progress - activity is empty
Thanks
- 0GWGary Whitehead ·
Henry, Are you preserving
Henry,
Are you preserving early dates when resource levelling? If not, I don't see the need for both early and remaining ealry start in your filter?
An obvious thing to do would be to find one of the offending activities which is not being shown but should be, and investigate it's physical percent complete, early start, and remaining early start to see which condition it is failing on.
- 0AAAlex Alex ·
Henry, i guess your filter
Henry, i guess your filter conditions to identify ongoing activities are not correct. For example, your condition "Where Early Start is within range DD DD+3W" will exclude many activities which had an early start before the data date but presently ongoing.
- 0SHShah. HB ·
Hi Henry Chiu You can try out
Hi Henry Chiu
You can try out by using following condition (If you are looking for 3 Weeks Look Ahead layout)
All of the following
Start Within range of DD DD+3W
Activity % Complete less than 100%
Cheer's
Shahul
- 0RBRon Beechey ·
Henry Above is what we use
Henry
Above is what we use and it will give the work through tasks that start before the start date and then have a duration longe than the 3 weeks. It is 2 filters
T0-T2 - Date Range:
Where (Any of the following)
Where Finish is greater than DD-20H
And Start is less than or equals DD+508HSimply sets thedate range
T0-T2 - Core:
Where (Any of the following)
Where Activity Status equals In Progress
Or Activity Status equals Not Started
And (Any of the following)
Where Activity Type equals Resource Dependent
Or Activity Type equals Task Dependent
Or Activity Type equals Finish Milestone
Or Activity Type equals Start Milestone
Try this and you may want to adjust as needed
- 0JAJeelani amin ·
Salam, I hope u all r fine
Salam,
I hope u all r fine by the will of Almighty.Here is the filter formula for 3 weeks lookahead.
Parameter Is Value
Remaining Early start in the range of DD
High Value
DD+3w
0R Activity Staus Equlas IN Progress.
( if u want to show on going activities in progress)
Regards
Jeelani
- 0RDRafael Davila ·
Timo,What you are describing
Timo,
What you are describing seems like project truncation, a functionality to my understanding not available in P6. Similar but not equal functionalities, one complement the other but are not a substitute of the other.
Activities in progress mean activities scheduled to happen on DD, can finish within the lookahead range or after.
When you are filtering for a lookahead you want to see the portion of the bars of these activities that occur before and or after the DD range. You want to know their past performance and future projection, different than when interested in truncation.
For a 14 days lookahead you need to filter for:
A) Activities in progress (starting before DD and finishing after DD)
........1. In progress (I believe it to be a predefined filter in P6 perhaps Activity % Complete is less than 100%), or
B) Activities starting within 2 weeks (does not matter when do finish); DD </= Start </= DD+14
........2. Start >/= DD, and
........3. Start </= DD+14
Roger suggestion seems like will do it, he uses P6 and is following the functionality of the software.
I use Spider Project and use a filter to exclude [NOR] activities finishing before DD or activities starting after DD+14. This makes it easy to create a filter for any date range, an interactive filter available in some software but in this way you do not have to enter the dates every time, convenient to automate printing of report groups.
With truncation you isolate the duration, cost and resource usage outside the truncation range.
The following illustrates some of the differences between a range filter and truncation for Nov 14 to Nov 20 [ DD 11/07/2011 16:00]. Take a look not only at costs but also to remaining duration.
Best regards,
Rafael