Does Max Units/Time links with any thing

Muhammad AsimMember for 15 years
Created
2
2
0

Hi:

My question is that, does Max Unit/Time link with any thing?

I am using

Max Units/Time = 2h/d

Price/Unit  = 12/d

Default Units/Time = 8h/d

Duration = 10d

This gives me Budgeted Units = duration x Default Units/Time = 10h/d x 8d = 80h

When I assign this to activity with 10d duration the

laboure Cost comes with = Budgeted Units x Price/Unit = 80h x $12/h = $960 (for 10 days)

But where is Max Unit/Time which 2h/d ? Does this not link with any thing? Or my calculations are wrong?

2 replies

Oldest first
  1. 0
    Amit Parmar (PMP) ·

    Hi Asim,Max Units/Time is

    Hi Asim,

    Max Units/Time is used for resource levelling and does not have any effect it Total Units calculation. If a resource can work only 8 hours a day and you assign it to multiple activties and total working hours exceed 8 then it will show over-loading. This is particularly helpful when you arre using labour resources.

    Regards

    Amit

    Check out my blog on Primavera at http://www.primaverablog.in

  2. 0
    Aries Arian ·

    Hi AmitYou have not Included

    Hi Amit

    You have not Included Risk Anaylysis in You Blog?

    Regards

    Arian.