Skip to content

Recurring Task in Primavera 6

Abdullah MerchantMember for 15 years 10 months
Created
2
3
0

Is it possible to create a recurring task in Primaver 6, as we do it in MS Project 2007. Im in the process of creating a Maintenance Schedule for Plant Utilites like chillers and air compressor. I want the dates to fall on a particular week or day of each year. We already have a schedule created in SAP 6.0, but i thought i could use the Primavera 6.0 to schedule as per the availability of the resources.

Please help if there is way to create a recurring task in P6.

2 replies

Oldest first
  1. 0
    Alex Alex ·

    You can create a calender

    You can create a calender with just the working days you want the recurring task to happen. Then apply the recurring task to this calender with the duration same as the number of recurrence.
  2. 0
    Abdullah Merchant ·

    Thank You Alex,But i think

    Thank You Alex,

    But i think that will require a lot of calendars. Im trying to see if can create a Plant Maintenance schedule for various Plant Equipments, around 500 in all. Now most of these activities will have to be repeated after 6 months and some are to occur every 3 months. So i want to have the same task showing with 4 different Start and Finish Dates.

    Example:-

    PM of Air Compressor

    This activity should be visible as four separate activities of the same name having their starts spnned out after 3 months. Like the way it is possible in MS Project 2007.

    So is there a separate way to do this.

    Regards,

    Abdullah Merchant,PMP

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?