P6 - Resource Units Graph not spreading resources correctly

Bill LusterMember for 14 years 11 months
Created
5
3
0

I have loaded my P6 schedule with 17 resources and I have entered "planned" units resource numbers for each resource/each activity.

When I pull up the resource graph, the planned units only show up in the first month (for example: 3 month activity with 96 hours... all 96 hours are in month one). 

I know this is a setting somewhere.  I've searched, but no luck.

Thanks!  Bill

5 replies

Oldest first
  1. 0
    Alex Alex ·

    Anything to do with resource

    Anything to do with resource curve type? Front loading or manual curve settings?
  2. 0
    Bill Luster ·

    No.  I am not using any

    No.  I am not using any resource curves.  I did some searching.  There are some different things I can try. 

  3. 0
    Scott McComb ·

    You can try setting the

    You can try setting the "Resource Units/Time" for each activity to a value that gives you an even spread over the duration of the activity.  You can add a column "Resource  Units/Time" column in your Resource tab.  You will have to provide a value for each resource in each activity. 

  4. 0
    Shah. HB ·

    Hi BillCheck the histogram is

    Hi Bill

    Check the histogram is for selected activities or for all activities 

     

    Cheer's

    Shahul

  5. 0
    Bill Luster ·

    "You can try setting the

    "You can try setting the "Resource Units/Time" for each activity to a value that gives you an even spread over the duration of the activity.  You can add a column "Resource  Units/Time" column in your Resource tab.  You will have to provide a value for each resource in each activity. "

     

    I'll be trying that on Monday morning...  That was also recommended by a co-worker, but I didn't have a chance to try it today.  To busy!!!

     

    Thanks for your help!

     

    Bill................