Flaws in P6 – Setting an ongoing program as Baseline
In the Open Standard
Haresh JayanthMember for 20 years 1 month
- Created
- 0
- 5
0
Dear All,
Why P6 can’t shows correct dates of Start and Finish (BL Start & BL Finish), if we set an ongoing program as baseline program. When we insert baseline column of an ongoing program, most of the activities, which are already completed are showing different dates. The problem can be solved by inserting a column called BL Actual start and BL Actual Finish. But when we insert these two columns, the forthcoming activities cannot be seen? How to solve this problem.
regards,
Haresh Jayanth - PMP , PSP