Error with labor units
In the Open Standard
Dinh KhanhMember for 14 years 11 months
- Created
- 0
- 1
0
Hi all,
I'm very new to P6, so I'm sorry if my question is a stupid one or be duplicated.
When I change the duration parameter as the following figure (80% in this case):
The trouble is raising with Labor Units:
Their budget was set as 640
With the change of duration, my expectation is the remaining should be: 640 - 512 = 128 instead of 320 as you see.
How can I overcome this trouble?
Thanks for your support.
Replies
Oldest firstNo replies yet. Be the first to answer.
Log in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?