How do I show the histogram of any resource in the sheet I want to print? Primavera P6

Tomas OsorioMember for 14 years 11 months
Created
1
2
0

Hi everyone.

 

I want to show the usual schedule and also the histogram in the same sheet I want to print in Primavera P6.

 

Waiting for your comments..

 

Tomas

1 reply

Oldest first
  1. 0
    Shah. HB ·

    Hi Tomas Osorio In the Bar

    Hi Tomas Osorio 

    In the Bar Chart Layout Select the resource histogram option which is available in tools bar's,then go to print preview option under page set up  choose the tab named ""option"" which lies near to footer in that check mark the profile 

     

    Cheers

    Shahul