Relationship lines colour change in P6 v7.0

Lalit SisodiaMember for 17 years 11 months
Created
5
2
0

Hello Planners,

Does anyone jnow how to change the reelationship lines colour in P6? It wasa there in P3 and even in Suretrak!

5 replies

Oldest first
  1. 0
    Ron Beechey ·

    I believe it can not be done

    I believe it can not be done

  2. 0
    Alexandre Faulx-Briole ·

    Lalit, are you sure?in

    Lalit, are you sure?

    in Primavera softwares, relationship lines colour are significant: red is a driving critical relationship, black solid a driving non critical, black dotted a not driving

    therefore, you cannot change the colours

    Alexandre

  3. 0
    Bruno Ponraj ·

    can anyone suggest how to

    can anyone suggest how to change the red line to black ( critical to normal)

  4. 0
    Santosh Bhat ·

    You don't get to decide which

    You don't get to decide which activities (and therefore relationships) are citircal or not, its a function of the underling CPM calculation of activities.

  5. 0
    Zoltan Palffy ·

    yes red critical non critical

    yes red critical non critical black

Log in or join to reply