How can I show the late baseline bar on the layout?

Ayman EleishMember for 15 years 9 months
Created
4
2
0

Dear All ,

Can I show the late baseline bar on the layout?

Thanks and Regards,

4 replies

Oldest first
  1. 0
    Alexandre Faulx-Briole ·

    Ayman,I am afraid there is no

    Ayman,

    I am afraid there is no early and late baseline bars in P6 as there was in P3; as far as I know, P6 only manages early bars when you maintain and assign baselines

    Alexandre

  2. 0
    Ferdinand U. ·

    you can try to create UDF for

    you can try to create UDF for late bar using excel import/export copied from your baseline late dates

  3. 0
    Ferdinand U. ·

    you can try to create UDF for

    you can try to create UDF for late bar using excel import/export copied from your baseline late dates

  4. 0
    David Kelly ·

    Copy the baseline you want

    Copy the baseline you want the dates from (P6 v7 lets you do this in place)

    Restore the baseline to the live EPS

    Open the project you just restored

    Run a global change to set :

    Planned start = Late Start

    Planned Finish = Late Finish

    Demote the project to being a baseline again

    Use that baseline - set it as secondary or tertiary - and as with ALL BASELINES it uses the planned dates to draw a bar.