Skip to content

Filtering of activities in P6

Kannan CPMember for 18 years 4 months
Created
21
13
0

Hi Friends,

How to fiilter the activities of a particular month, which neither starts nor ends in that particular month, but will be in progress stage during that month. Assume as a baaseline schedule

For eg:

Activity 1: Dec 2011 to Jan 2012

Act 2     : Feb 2012 to Sep 2012

Activity3: Apr 2012 to Oct 2012

Activity4: Nov 2012 to Dec 2012.

I want to filter and see the activities during the time period of Aug 2012. Activities 2 & 3 are passing through the Month Aug 2012.

I filtered both with Early start/Early finish & start/finish-with in the range of Aug 01 & 31. but its not working.

Can somebody advise me with a solution.

Thanks

Kannan

21 replies

Oldest first
  1. 0
    Rafael Davila ·

    I do not use P6 but the

    I do not use P6 but the following set of conditions can be a way:

    • Condition 1: activities starting within the date range.
    • Condition 2: activities finishing within the date range.
    • Condition 3: activities starting before the date range and finishing after the date range.
    • Condition 4: activities starting and finishing within the date range,

    Learn to use the operators, any activity that complies with Condition 1 OR Condtition 2 OR Condition 3 OR Condition 4 will make it.

    Best regards,

    Rafael

  2. 0
    Ferdinand U. ·

    Rafael's reply is the answer

    Rafael's reply is the answer to any filter lookahead date problem

     

    for your situation, condition 3

     

    Filter specs should be:

     

    All of the following

    Start is less than or equals 01-Aug-12

    Finish is greater than or equals 31-Aug-12

  3. 0
    Shareef Abdul Azeez ·

    1.jpgThis is how the Filter

    This is how the Filter Coniditions given by Rafael would be in P6 and it works !!!

     

    Regards

    Shareef

  4. 0
    Kannan CP ·

    Thanks a lot Rafael,

    Thanks a lot Rafael, Ferdinand, Shareef.

    Now its working.

    Regards

    Kannan

  5. 0
    dulat Praliyev ·

    HiCan you explain how to

    Hi

    Can you explain how to working filter?

  6. 0
    Arneil Cagas ·

    hi,kannan, open ur project,

    hi,kannan,

     

    open ur project, go to group & sort,group by select start , and  select a Month if group interval

     

    and then apply, ok.

     

    vty/Arneil

  7. 0
    Ramshad kuniyil ·

    Hi rafael,i want to filter

    Hi rafael,

    i want to filter the activities as condition 4 like you mentioned above. i did by puting start date greater than or equal to august 1 and finish date less than or equal to august 30. but its not showing all the activities. it is showing only finished activities. i need all activities within the range

     

     

    best regards

  8. 0
    Rafael Davila ·

    Learn to use the operators,

    Learn to use the operators, any activity that complies with Condition 1 OR Condition 2 OR Condition 3 OR Condition 4 will make it.

    ==>> Do not use AND operator.

    BTW as long ago I stopped using Primavera each day it passes it becomes more difficult to understand it.

  9. 0
    Zoltan Palffy ·

    I dont know what your data

    I dont know what your data date is but here is a solution

    solution #1

    filter 

    where

    Paramenter       is                                   value                high value

    start               is within the range of        aug 1, 2012       aug 31, 2012

    or

    Finish                is within the range of        aug 1, 2012       aug 31, 2012

    or 

    activity status              equals                     inprogress

     

     

  10. 0
    Rafael Davila ·

    How to filter the activities

    How to filter the activities of a particular month, which neither starts nor ends in that particular month, but will be in progress stage during that month?

    How in progress filter will find out if will be in progress a few months after Baseline DD?

    In progress between Aug. 1, 2012  -  Aug. 31, 2012?

    I am not a P6 user any longer but maybe the above can be specified, in such case it should be enough to make the filter.

  11. 0
    Zoltan Palffy ·

    I posted the p6 answer

    I posted the p6 answer

  12. 0
    Robert Bell ·

    It doesn't matter much, but a

    It doesn't matter much, but a slightly quicker way to filter for a particular period is;

    Where Start is less than 31-Aug-12

    And Finish is Greater than 01-Aug-12

  13. 0
    Rafael Davila ·

    Robert, your solution is very

    Robert, your solution is very good, as we say at home very much better!

    BTW as far as I can recall MSP have such filter pre-defined under the name of Date Range Filter.

  14. 0
    Meurig Davies ·

    Hi All,How to fiilter the

    Hi All,

    How to fiilter the activities of a particular month, which neither starts nor ends in that particular month, but will be in progress stage during that month. 

    eg:

    All activities that fall within th date range 1st Jan to 31st Jan whether thay are planed to Start,Finish or pass through in Progress

     

    Thanks in Advance

  15. 0
    Meurig Davies ·

    Hi All,How to fiilter the

    Hi All,

    How to fiilter the activities of a particular month, which neither starts nor ends in that particular month, but will be in progress stage during that month. 

    eg:

    All activities that fall within th date range 1st Jan to 31st Jan whether thay are planed to Start,Finish or pass through in Progress

     

    Thanks in Advance

     

    Meurig

  16. 0
    Zoltan Palffy ·

    MeurngYou have to at lest

    Meurng

    You have to at lest tell me what month you are looking to pass through ?

    I think you are looking for 

    activity status  equals in-progress

    this will list any activities that have started but are not yet done.

  17. 0
    Meurig Davies ·

    I am looking to pass through

    I am looking to pass through January when it will be planned to be in progress.

     

    Regards,

     

    Meurig

  18. 0
    Zoltan Palffy ·

    KannanfilterANY where start

    Kannan

    filter

    ANY where

     

    start is within the range (low value) 8/1/201 and 8/31/2012 (high value)

    or finish is within the range (low value) 8/1/201 and 8/31/2012 (high value)

  19. 0
    Zoltan Palffy ·

    Meurigif you only want to

    Meurig

    if you only want to find passing thru Jan 2020 then

    filter 

    all

    where Start is less than Jan 1 2020

    and 

    finish is greater than Jan 31, 2020

     

    also if you want activities that happen during Jan 2020 you will need to use 2 filters 

    use the 1st one I listed and add a 2nd filter

    any 

    where start within the range Jan 1 2010 (low value) and Jan 31  2020 (high value)

    or where where finish within the range Jan 1 2010 (low value) and Jan 31  2020 (high value) 

     

  20. 0
    Meurig Davies ·

    Thanks for you help Zoltan.

    Thanks for you help Zoltan. Your solution works perfectly.

     

     

    Regards,

     

    Meurig

  21. 0
    Zoltan Palffy ·

    Meurig Glad I could help you

    Meurig 

    Glad I could help you

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?