Baseline Milestones

David CraigMember for 17 years
Created
1
2
0

Hi Everyone,

                 Im just going to jump striaght to the point. Basically I have created a small programme for a construction job. I have created a baseline for this job to track against original dates. The problem is when i tick the boxes for displaying baseline bars and milestones, the baseline milestones follow the current project milestones. I added the columns in for baseline start and finish, which display the correct dates for the milestones. I just dont understand why the graph is showing the baseline milestone at the same date as current project milestone. Any help is greatly appreciated.

 

Best Regards,

 

David

1 reply

Oldest first
  1. 0
    David Craig ·

    I have managed to solve this

    I have managed to solve this issue now. Just got mixed up between Project and Primary baseline options.

     

    Thanks

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?