question about labour units in P6

Yaser A. Al-BustanjiMember for 16 years 5 months
Created
1
2
0

Hi all,
I have found a problem in my primavera program. I didnt assign any labour type resources to the activities of my program. But in Budget Labour units column, Primavera is showing some values? 
Why it is coming like this?

Thanks in advance.......

1 reply

Oldest first
  1. 0
    Raymund de Laza ·

    Hi, You might  have copied

    Hi,

    You might  have copied your program from other programs that have labors assigned in the activities.

    Yo need to reset labor units of all activities to zero.

     

    Regards,

Log in or join to reply